Council approves USDA watermain change order as water and wastewater projects continue

Jun 2, 2025

Wightman & Associates updated council that drinking water and cleanup work has begun while wastewater sludge removal was delayed; the council approved USDA Watermain change order #5, increasing costs by $30,750.00.

The full story

Andrew Rudd of engineering firm Wightman & Associates updated the Village Council on the community's USDA-funded water and wastewater projects, saying, "Drinking water, top-soil and cleanup have started and will continue." He told the council that final walk-throughs will be scheduled soon but some adjustments shifted the final completion timeline.