County provides update on battery storage site at State Road 3; first unit expected this week
Aug 17, 2026
Officials said intersection widening is complete for the battery storage project near State Road 3 and the first unit was estimated to be placed during the week of Aug. 17, 2026, with container deliveries every 10–12 days.
The full story
Highway staff reported progress on a battery storage project near State Road 3: the intersection widening work is finished, and crews are coordinating deliveries and temporary measures ("bridge jumpers") to accommodate battery containers. Staff estimated the first unit would be placed during the week of Aug. 17, 2026, and that additional container deliveries were expected every 10–12 days.