Oct 5, 2026
Utilities Director Kent Footh reported an $8,147 quote to integrate the wastewater plant UV system into SCADA for remote monitoring, a Schwab‑Eaton water‑system study with preliminary results expected in 1–2 weeks, a new water plant hire, and recent pickup repairs costing just under $2,000.
The full story
Utilities Director Kent Footh told the council about several near‑term utility projects and staffing developments during the Oct. 5 meeting.