Board ratifies unplanned amendment for Root Street reconstruction after field issue
Aug 12, 2026
Staff asked the board to ratify a previously executed contract amendment with F.W. Carson Company adding cement treatment to the new base on Root Street after unanticipated water conditions were discovered; the board ratified the work unanimously so construction could proceed.
The full story
Casey Sylvester, transportation and traffic engineer, told the board crews encountered unexpected water issues while opening the road and the contractor executed work to address the condition. "This amendment is for cement treatment of the new base to bolster the road bed," Sylvester said, adding that the work was already executed and that staff sought ratification for transparency.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →