Engineer: RSA drainage plans advancing; apron rehab advertised to bid

Mar 18, 2026

Wood Rogers engineer Brian Martinez Smolos reported 60% plans were delivered for the RSA/drainage improvements and the main apron rehabilitation was advertised to bidders; the ACIP will go to the Board of Supervisors for formal approval the next day.

The full story

Brian Martinez Smolos of Wood Rogers updated the authority that the RSA, drainage and improvements project has reached 60% design and has been submitted to the FAA ADO; the consultant said the project is progressing toward 90% plans with an objective to advertise for bids in the May timeframe to align with grant deadlines. "So, we are moving forward on that with the goal of opening bids before... basically May timeframe so that we can be ready for the grant," he said.