Emergency-access relocation for Scott Center raises interjurisdictional permitting concerns

Apr 10, 2026

The Scott Center’s revised site plan shifts emergency access through a City of Detroit parking parcel, prompting questions about Detroit permitting, how access agreements with Saint Ambrose will be secured and whether occupancy can proceed before those approvals are finalized.

The full story

The Scott Center’s amended site plan submitted to Crosspoint Park’s planning commission relocates emergency access to connect through a neighboring City of Detroit parcel, a change that requires Detroit’s approval before a city-issued permanent certificate of occupancy is released. Commissioners pressed consultants and staff about whether Detroit could complete permitting in time for the center’s planned May 16 opening and whether a temporary certificate of occupancy is a viable stopgap.