Board approves expanded contract and extended timeline for Lincoln County Commons project

Oct 21, 2026

The board approved an amendment to the project‑management contract with DPM Company after the Lincoln County Commons project scope grew from an initial $10–12 million estimate to about $46 million; project‑management fees remain below 1.8% and the schedule is extended roughly 13 months toward late 2028.

The full story

County counsel told commissioners that the Lincoln County Commons capital project’s scope has increased significantly and that the request before the board would extend the project‑management contract to allow construction to finish. Counsel said the project, originally estimated at $10–12 million, is now roughly $46 million and that project‑management fees would remain under 1.8% of the total project cost.

The contract amendment extends the manager’s period by roughly 13 months; counsel said that, with the change, the board should expect project completion near the end of 2028. Commissioner Chuck moved to approve the amended agreement with DPM Company for project management; the board approved the motion by voice vote.

The meeting record provides the revised cost estimate and the fee percentage cited by counsel; specific contractual payment schedules and funding sources were not read into the record during the discussion.