Audit flags missing lifecycle and operating-cost data across Wadsworth capital projects

Jun 11, 2026

An internal audit of eight major Wadsworth capital projects found consistent gaps in lifecycle cost analyses, annual operating/repair estimates and feasibility documentation and recommended completing the 15-year CIP and a standardized project checklist.

The full story

An internal audit report prepared for the City of Wadsworth's Audit Committee was asked to be considered at the committee's June 11, 2026 meeting. The report reviewed documentation for eight major capital projects and found that, while authorization, design and procurement records generally existed, project files often lacked information needed for long-term financial planning.