Council approves Pine Street overlay under budget; transcript shows contractor-name discrepancy
Oct 20, 2026
Oct 20, 2026
Council approved a Pine Street paving contract after staff reported the low bid came in well under the $250,000 budget at $142,003.65. The meeting transcript lists the low bidder as "Leduc Construction" in presentation remarks but the motion names "Duke Construction LLC"; the council voted to award the contract.
The full story
Councilors approved a contract for the Pine Street overlay project (1st Street to 5th Street) after staff reported a low bid far below the project budget. Staff said the low bid was $142,003.65 against a $250,000 appropriation and described the work as primarily an overlay with limited grinding and modest widening in narrow locations.