Council ratifies WWTP change orders adding manhole and extending contract time
Oct 5, 2026
Oct 5, 2026
Levelland council ratified two change orders for the Wastewater Treatment Plant project, including a $30,030 manhole addition to serve the HET facility and an increase in contract time from 470 to 500 days due to weather delays.
The full story
The Levelland City Council unanimously ratified Oct. 5 the City Manager's signature on two change orders for the Wastewater Treatment Plant construction project.