County approves large Meadowbrook sewer change orders and related engineering modifications

Oct 21, 2026

The board approved a $519,522.30 change order to Woodford Excavating for Meadowbrook sanitary sewer work, a $517,610 modification to Burgess & Niple's engineering agreement, and awarded a $4,874,775 contract to Pollard Land Services for Caleb Road sewer work.

The full story

The Board approved change order #5 with Woodford Excavating LLC that adds up to $519,522.30 to Contract B of the Meadowbrook Sanitary Sewer Improvements Project (revising the contract total to $5,794,497.06). The change order covers additional asphalt replacement and resurfacing with striping along Meadowbrook Drive; the agenda stated the cost will be paid by Ohio EPA Water Pollution Control funds.