Change order substitution for Decatur wastewater lagoons would save $25,550 by using Flexamat instead of riprap

Dec 2, 2024

Wightman recommended council accept Change Order No. 2 for Contract B, substituting Flexamat permanent erosion control for MDOT-standard riprap on lagoon work; the change reduces the contract by $25,550 to $1,859,200 and is presented as a cost-saving measure supported by the contractor.

The full story

The packet asks the council to receive a presentation from Andrew Rudd, P.E., of Wightman & Associates and to approve Change Order No. 2 for Contract B (Wastewater Stabilization Lagoon Improvements).