Wheelock road crew reports culvert replacements, grading hampered by drought; septic riser work completed

Oct 9, 2025

Road foreman Chuck Dill told the Selectboard three failed culverts were replaced, ditch work was done with a rented excavator, grading is delayed by drought, and town hall septic riser lid replacement will cost $350; Chuck said he will meet a Better Roads grant representative about Morgan Rd East.

The full story

At the Oct. 9 meeting Road Foreman Chuck Dill updated the Selectboard on ongoing road maintenance, reporting that three culverts that failed in March have been replaced and that the town rented an excavator for ditching and work on Vertical Mile, Blakely, John Rock and Sutton Roads.