Section 32 of the CS conditions abatement and AVT eligibility on developer payments: $40 million deposited into an impact fund within 60 days of phase-1 FID and a contractual commitment to another $40 million within 60 days of phase-2 FID, with regulatory oversight by the Department of Commerce.
The full story
Committee staff explained the CS conditions eligibility for abatement and the alternative volumetric tax on developer payments into a municipal impact fund. The CS requires the primary property owner to deposit $40,000,000 into an impact fund within 60 days of a final investment decision (FID) on phase 1 and to commit contractually to a second $40,000,000 within 60 days of FID on phase 2.