Commission approves change orders to extend construction oversight and testing for Decatur Square Transformation

Sep 8, 2026

Change orders were approved to extend Jacobs Engineering construction management ($84,430) and Matrix Engineering testing/inspections ($7,745) for the Decatur Square Transformation project after unforeseen utility and MARTA-structure delays pushed completion into November 2026.

The full story

Deputy City Manager Junger told the commission the Decatur Square Transformation contractor encountered unforeseen utility conditions and issues related to MARTA’s structure that delayed Phase 2 of the work. To maintain oversight, Junger recommended a change order of up to $84,430 to Jacobs Engineering to extend construction management services; the amended Jacobs contract would total $533,550. He also recommended Change Order #1 to Matrix Engineering Group for up to $7,745 to continue materials testing and special inspections through the extended schedule.

Junger said Phase 2 work was expected to take three months and that construction is now anticipated to conclude in November 2026; both change orders were approved with all present voting "aye." Staff said funds for these change orders were available in the project budget.

Written with AI from the event video and transcript. Check it against the source ↓