Contractor cites poor soil, mobilizes sheet‑piling; foundations likely push into December
Aug 25, 2026
Project manager Paul Yurinek told the board poor soil at two seawall locations forced a switch from sprayed gunite to sheet‑pile installation, delaying foundation completion and likely pushing 'substantial commencement' into December — threatening a November grandfathering deadline.
The full story
Paul Yurinek updated the board on the Port Clyde/Colby project, reporting that excavation exposed unstable soils at two seawall locations and that an initial gunite spray did not provide sufficient stabilization. He said the contractor H.B. Fleming mobilized immediately to install sheet piles around areas adjacent to the fuel tank and near Monhegan Boat Lines to prevent bank collapse and protect neighboring properties.
"As they say, better to be safe than sorry," Yurinek said, describing the mobilization of the sheet‑pile contractor. He told the board design drawings are about 75–80% complete and the team is pursuing panelized wall construction and a cross‑laminated‑timber elevator shaft to speed building assembly. When asked whether the team could meet a November deadline to maintain grandfathered status, Yurinek said he could not confidently commit to finishing foundations by November and expected foundation completion to slip into December; he offered to meet with town staff to discuss off‑site work that might demonstrate substantial commencement.
Written with AI from the event video and transcript. Check it against the source ↓