Martin Drive pump station nearing completion; parallel sewer and easement work continue

Oct 20, 2026

CCUSA reported Contract A (pump station) should be complete this autumn, Contract B (parallel gravity sewer to Farfields Drive) awaits developer work, and Contract C is slated for spring 2027; Contract D is paused for funding and easement work.

The full story

CCUSA staff updated the boards on the Martin Drive wastewater project. Contract A (the new pump station) is expected to be complete in the autumn (probable November) and is designed to pump 600 gallons per minute to the Dreaming Creek interceptor. Contract B — a parallel gravity sewer and force main to Farfields Drive — is substantially complete, but CCUSA is waiting for developer Camden Village LLC to construct parallel pipes through its development before the system can receive flows.