Zytel outlines build plan, crews and 2027 completion target for Patrick County
Sep 29, 2026
Sep 29, 2026
Zytel’s COO told the board the company will deploy 20–25 crews from Stuart, build from the primary circuit outward, and expects to meet grant substantial-completion deadlines in 2027; Zytel said it will activate customers as segments are completed.
The full story
Rodney Graham, chief operating officer for Zytel, told the board Zytel plans to build from Stuart outward and will activate customers as sections are completed. Graham said the '2022' and '2023' grant projects have hard deadlines for substantial completion—one by June 30, 2027, and another by Dec. 31, 2027—and that failing to meet those deadlines could risk federal grant funds. He said, "It will be completed in 2027."