Developer: load study shifts full‑power availability to 2031; breakers and FirstEnergy timing at issue

Feb 3, 2026

Capacity LLC told the committee that a detailed load study moved the expected timeline for full 500 MW service from late 2028/early 2029 to about 2031 because FirstEnergy is signaling different breaker requirements; the developer said possible remedies include sourcing higher‑capacity breakers or buying land and equipment for the switchyard.

The full story

Developer Will Turner told the committee the project's conceptual schedule anticipated a substation by late 2028 or early 2029, but a detailed load study returned a later in‑service date of roughly 2031 because required breaker capacity and factory slot availability changed expected equipment lead times.