Committee hears schedule update; OPM, design and CM outline prequalification and 60% CD timeline

Oct 22, 2026

OPM and the design team reviewed an updated schedule including a moved estimator date (Nov. 11) and a December 16 target for the committee motion to submit the 60% construction documents (CD) to MSBA. The team outlined a prequalification committee and multiple public prequalification meetings for early-bid packages.

The full story

Chris, the owner’s project manager, reviewed the updated project schedule and said the team moved the estimator submittal two days earlier (from Nov. 13 to Nov. 11) to allow more time for reconciliation and value-engineering discussions before the committee meeting.