Staff seeks $27,500 budget amendment for GDOT-required lighting design at Coal Springs Rd roundabout
Oct 27, 2026
Justin said GDOT requires an approved lighting plan for the Coal Springs Road/SR 53 roundabout; Walton EMC declined to provide the design and staff will request a $27,500 contract with SCI to prepare the plan and related budget amendments next week.
The full story
Justin told the board the Coal Springs Road/SR 53 roundabout design requires a GDOT-approved lighting plan. He said Walton EMC declined to design the lighting and staff proposes contracting SCI to prepare the required plan for $27,500, with associated budget amendments to follow for board approval next week.
"So what you have before you is a budget amendment, with SCI, who is the designer of the project for $27,500 to include a g dot required lighting design," Justin said. The board heard the update and staff will return with the necessary budget items and recommended approval.