Xcel Energy told Monticello council that Minnesota’s 2025 law and an Xcel tariff (PUC-approved May 2026) require large data-center customers to shoulder interconnection costs, provide financial security, accept a 15-year minimum service commitment, be billed on at least 80% of contracted demand, and face exit fees for early termination.
The full story
Xcel Energy representatives Jake Andre and Scott Johnson told the Monticello City Council that the company’s large-load tariff — adopted with modifications by the Public Utilities Commission in May 2026 — contains explicit protections intended to prevent cost shifts onto existing customers when very large users such as data centers connect to the grid.