Developer seeks stream-buffer variance for South Main Street development; council asks for state/federal permits

Apr 7, 2026

A developer seeking to add parcels and roughly 29 acres to a mixed-use project asked Jonesboro for a variance to encroach into a stream buffer; planning staff recommended approval conditioned on demonstration of compliance with Georgia Soil and Water and any federal requirements before city permits issue.

The full story

Planning staff presented a variance request from Matt Kouton for an approximately 29.14-acre mixed-use development in the Gateway South overlay district that would encroach into an on-site stream buffer to accommodate access and utilities. Staff said an alternative site plan would avoid the encroachment but would eliminate about 68 dwelling units and might risk funding tied to unit counts.