Harrison approves change orders, narrowly backs $2,399 generator regulator replacement
Oct 28, 2026
Oct 28, 2026
The board approved a package of change orders (net savings $40,923.31) and individual items including a $79,860 concrete alternate and a $123,182.31 credit; a $2,399 regulator valve replacement drew dissent and passed 5–2 after trustees debated who should bear the cost.
The full story
The board approved multiple construction change orders presented by staff, including a $79,860 alternate for concrete at Fire Station 70 and a deduct of $123,182.31 for temporary heat not used during construction, yielding a net change of a $40,923.31 savings. A motion to divide the bundle into separate votes passed 5–2 and the change orders were taken individually.