Deputy Chief Engineer Katie Oakley briefed the board on the annual CIP, highlighting the Terry Ranch pipeline (segments 1—2 complete; $65M to date), the Gold Hill 60-inch connection (remaining 3 miles, anticipated 2027—128 construction), lead-and-copper replacements (~$14M total), and downtown revitalization with $47M overall of which water and sewer share $13.5M.

The full story

Deputy Chief Engineer Katie Oakley delivered the Water and Sewer Department—1s annual capital improvement program update on Oct. 21, outlining near-term schedules and cost-to-date figures for major projects.