Board discusses and authorizes contingency‑funded testing with Medco

Oct 20, 2026

Staff said contingency funds would cover compaction and concrete testing and that Medco provided the quote; board members treated the testing as within an already‑set contingency and approved proceeding at the quoted, not‑to‑exceed cost.

The full story

During discussion of item 9, staff said contingency funds are available to pay for testing services and that Medco provided a quote to perform compaction and concrete testing. Staff described the procurement as nearly sole‑source in practice and told members the work would be done within the contingency the board has already set aside.