Owasso reports progress on Garnett Road, US‑169 and multiple intersection projects

Aug 4, 2026

Public works staff told the council Garnett Road water/storm work is about 90% complete with paving continuing and a likely October–November finish; multiple intersection and utility-relocation projects were updated with completion targets ranging from late 2026 to mid‑2027 and a public meeting set Aug. 13.

The full story

City public works staff presented the monthly project status report, highlighting progress across multiple road and utility projects. On Garnett Road (106th to 116th Street North) staff said water and stormwater line installation is approximately 90% complete and concrete paving has advanced to about 112th Street; staff estimated final completion in October–November. The presenter said, "If you've been up on Garnett lately, concrete paving... they've got paving now up to about 112th Street," and that crews will switch traffic onto new concrete and begin northbound paving soon.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in