Staff reports: Spring Street interceptor progress after successful horizontal boring; Rob retires

Oct 14, 2026

Staff reported successful horizontal boring under the railroad for the Spring Street interceptor, will submit for casing installation and expect 6–8 weeks for railroad approval; staff also announced Rob's retirement.

The full story

During the monthly reports, staff announced the successful completion of a small directional boring under the railroad for the Spring Street interceptor, clearing a key obstacle that had delayed the project. Staff said the next step is to submit to the railroad for installation of full casing pipe and that Union Pacific approval is anticipated in roughly 6–8 weeks.