Measure ES nearly complete, district reports about $2.6M available for final modernization work
Oct 28, 2026
Oct 28, 2026
Dr. Gooden reported that major Measure ES projects are finished (performing arts center, gym, band room, district office upgrades) and that after expenditures of a little over $90 million on a $92 million bond there are roughly $2.6 million remaining plus new state modernization funds expected in December.
The full story
Dr. Gooden provided the board with the annual facilities update for the Measure ES program and walked through recently completed projects and remaining closeout tasks.