Farline Bridge amendment would add $119,536 to Rambler Drive Little Pudding River bridge contract

Oct 21, 2026

Public Works requested Amendment #3 to PW-6067-24 adding $119,536.84 (est. $107,260.41 federal; $12,276.43 county funds) for change orders including slope stabilization, additional asphalt/aggregate and water-quality swale work, and extending contract completion to Oct. 31, 2026.

The full story

Marion County Public Works asked the Board on Oct. 21, 2026, to approve Amendment No. 3 to the construction contract with Farline Bridge, Inc. for rehabilitation work on the Rambler Drive SE Little Pudding River Bridge (PW-6067-24). The amendment adds $119,536.84 to the contract (new NTE $3,850,954.46) and extends the contract completion date to Oct. 31, 2026.