Staff reports Westside pump station, Rope Street and bridge projects making progress
Apr 15, 2026
Staff updated the board on capital projects: Westside Pump Station 'went vertical' and may be online by June 1; Rope Street pump station plans are ~90% complete and will be bid soon; the Whitechus Creek pedestrian bridge is ready for bidding pending abutment structural work.
The full story
In "other business" the city's project manager gave the board a progress report on several capital projects. The Westside Pump Station has advanced above grade, with product deliveries in hand and work scheduled to finish interiors; staff said they hope to have the facility online around June 1. Rope Street pump station design was described as roughly 90% complete and expected to go to bid by the end of the month.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →