Courthouse elevator delayed; contractor faces $1,000‑a‑day deduction if not finished by Sept. 20

Aug 20, 2026

Staff told the board the elevator contractor has struggled to source correct parts and expects completion by Sept. 20; contract language allows the county to deduct $1,000 per day for missed deadlines.

The full story

Staff updated the board that the courthouse/jail elevator remains under repair and that the company had difficulty obtaining correct parts, causing intermittent delays. The contractor now expects to finish work by Sept. 20 if no other issues arise.