Mathis council approves schedule-extending change orders for MIT grant projects; cost unchanged

Sep 14, 2026

Council approved three $0 change orders adding days to MIT grant projects: 61 days for generator work (new end date Nov. 3, 2026), 60 days for pier infrastructure (Oct. 30, 2026), and 63 days for sanitary sewer (Nov. 15, 2026); staff said the schedule remains within the Jan. 31, 2027 grant deadline.

The full story

The Mathis City Council on Sept. 14 approved three $0 change orders for work under GLO Contract No. 22-085-032-D275 (MIT Grant projects), each extending contract days to accommodate site conditions and fabrication schedules.