Engineers report progress on Mathis wastewater and water treatment work

Jul 13, 2026

Consultants reported Reytech is about 85% complete on a 24-inch wastewater line and ACP pier construction is roughly 96% complete; remaining work includes paving, final fencing and an access apron and a generator foundation extension at the water treatment plant.

The full story

On July 13, Manuel Guerra of LIA told the council that the wastewater installation contractor (Reytech) was approximately 85% complete on the major 24-inch wastewater line and that paving was expected to follow the pipe work. Guerra said ACP pier construction was approximately 96% complete with only final fencing and an access apron remaining.