Mathis approves $164,311 negative change order as Reytech sewer project nears completion

Aug 10, 2026

LJA told council the Reytech sanitary sewer project is roughly 90% complete with a 24‑inch line installed; Council approved Change Order #4 showing a negative contract impact of $164,311 and discussed using remaining funds for manhole rehabilitation.

The full story

Manuel Guerra of LJA Engineering reported that the Reytech sanitary sewer project is approximately 90% complete: the 24‑inch line has been installed and manhole rehabilitation work is ongoing. Guerra said an eight‑inch cleanout is needed and that a 12‑inch replacement line was required because of an insufficient drop at one location. Council discussed responsibility for remaining pothole repairs and the need for a joint inspection with Interim Public Works Director Manuel Ortiz and Reytech.