Utilities director lists immediate sewer, meter and line-rebuild projects

Apr 17, 2026

Fairburn utilities staff outlined immediate repairs and multi-year projects including emergency sewer main replacement on Fayetteville Road, Phase 3 AMI meter changeouts, and multiple overhead-line rebuilds plus Hwy 92 reconductor work.

The full story

Utilities Director Derek Hampton presented the Utilities Department’s organization, recent operational fixes and a list of capital and immediate-repair projects. Hampton said collections practices were strengthened, meter-reader positions have been filled and new SOPs were established to resolve issues such as meters reporting zero consumption for multiple months.