Council hears interceptor sewer update; approves two related change orders

Oct 8, 2026

City staff updated the council on the interceptor sanitary sewer main project; the council approved Change Order No. 3 (−$1,900) and Change Order No. 4 (+$24,398.19) during the Oct. 8 meeting.

The full story

The agenda listed Jess Hurlbert to provide an update on the interceptor sanitary sewer main project, but Craig Reinsch delivered the project update to the council on Oct. 8. Reinsch briefed members on project progress and related construction planning; the council recorded the update as informational and took no separate action on the status report.