Design timelines for Front Street and Seppala Drive projects pushed into 2027–28, engineers say

Jul 22, 2026

Engineers told the board Front Street design work was underway with a tentative 2028 construction schedule but staff said that timeline looks optimistic; Seppala Drive has not yet been advertised and may slip to 2027–28.

The full story

Officials updated the board on several capital projects tied to water and sewer design. The consulting engineer reported that the state DOT met to secure base maps for the Front Street-to-Stedman work and asked CRW for a fee proposal; the engineer's schedule currently lists 2028 for construction but staff expressed skepticism that the date will be met. "Their schedule indicates 2028 construction. Suspicious that that will be met," the presenter said.