Middle Clackamas interceptor delayed by permitting, to use SRF financing

Oct 29, 2026

WES said the Middle Clackamas interceptor will be financed with State Revolving Fund loans and that securing ODOT permits took multiple review cycles, delaying the project roughly six months as WES finalizes bid documents.

The full story

Stallard told members the Middle Clackamas interceptor project will use SRF financing and that obtaining ODOT permits required multiple review cycles, delaying the schedule by about six months. He said WES prioritized getting accurate traffic control and night-work details into bid documents to avoid underpriced or unworkable contractor proposals.