Commissioners probe payment schedule, retainage and GMP during construction-manager interview
Oct 29, 2026
Oct 29, 2026
Brown County commissioners and a construction manager candidate discussed invoice timing, retainage, bonds and the likely use of a guaranteed maximum price contract; Shellback outlined a pencil-draw invoicing cycle, monthly schedule-of-values and a standard 5% public-project retainage.
The full story
Commissioners pressed the construction-manager candidate on how invoices, retainage and potential lien issues would be handled for the county remodel project. The vendor described a process that begins with subcontractor invoices around the 20th, a contractor-prepared draft invoice on the 25th and a finalized invoice by the 1st of the month, with county payment windows determining when funds are released.