NEPA certificates received; CMP submitted and turtle-protection task authorized

Oct 28, 2026

Committee members reported receipt of NEPA certificates and that the conservation management permit (CMP) application was submitted; the committee authorized up to $2,000 for a turtle-management plan (task 1) if the permit requires it.

The full story

Staff reported that the NEPA-related certificates required for the project were received and that the next permit, the conservation management permit (CMP) under the Massachusetts Endangered Species Act (MESA), had been submitted with a $600 filing fee. Staff said they expect the CMP review to take roughly 30 days, which would fall around Nov. 6.