Commission seeks engineering proof of water, sewer and fire access for proposed RV park
Oct 8, 2026
Oct 8, 2026
Commissioners and staff sought stamped engineering plans showing meter sizing, sewer routing to the nearby manhole/lift station and proximity/flow of fire hydrants before construction may begin on the East Main Street RV park.
The full story
During the Oct. 7 hearing staff and commissioners questioned capacity and routing for water and sewer connections for the proposed East Main Street RV park. Staff said there is a small meter currently on the property and that the American Legion site nearby has water and sewer connections; engineering review will determine whether one or two meters or larger mains are required.