Sewer operator reports SCADA installation, dosing changes to lower electric use

Jun 11, 2025

Operators told trustees the treatment plant is meeting operational limits, a SCADA computer has been installed, and a dosing-pump matrix was adjusted to rotate run times — changes intended to lower electric usage.

The full story

The Village of Arpin Sewer Utility was told June 11 that the treatment plant is running within acceptable limits and that a SCADA computer has been installed to improve remote monitoring and control. The sewer operator also reported the dosing pump matrix was changed to rotate pump run times; staff said the change should lower electric usage.