Sewer operator: plant within limits; SCADA install set for May 27

May 14, 2025

At the May 14 meeting the sewer operator reported the plant "is running within acceptable limits," and noted SCADA installation is scheduled for May 27 and Alliant Energy transformer service for May 22. Maintenance work on UV racks and the lift station was also reported.

The full story

The sewer operator reported the Village of Arpin wastewater plant "is running within acceptable limits" and provided a short service schedule for upcoming upgrades. The operator said the SCADA installation is scheduled for May 27 and Alliant Energy transformer service is scheduled for May 22.