Board approves payment for screw press upgrade, orders feasibility study on digesters

Sep 14, 2026

Supervisors approved a $63,137.63 payment application to Eastern Environmental for the wastewater treatment plant screw press upgrade and authorized an Entech feasibility study to evaluate converting digesters from anaerobic to aerobic processing.

The full story

The board approved Payment Application No. 11 to Eastern Environmental for the wastewater treatment plant screw press upgrade in the amount of $63,137.63. Public Works Director Craig Conrad told the board the project is winding down and that Entech Engineering had reviewed and recommended payment.