Board authorizes PPL superload road‑use agreement for two transformer deliveries

Apr 27, 2026

Director Jason Reichert reported the Township received a Bay Crane request to allow two transformer superloads; the Board authorized a Road Use Agreement after a 4‑1 vote. The first delivery is tentatively scheduled the week of May 11, 2026.

The full story

Director of Engineering & Planning Jason Reichert briefed the Board on a Road Use Agreement request from Bay Crane Projects supporting PPL deliveries of two transformers by rail and road. Mr. Reichert said the deliveries "will be roughly 4 weeks apart, with the first transformer tentatively scheduled to arrive the week of May 11", 2026," and described the slow transport (approximately 3 mph) that will require State Police rolling guidance and temporary intersection closures.