Working Group hears construction timeline that will close most Maple Grove spaces through 2027–28

Oct 28, 2026

Staff outlined a phased construction approach: Grove Cove Aquatic Center closed Sept. 2026; gym and teen center close March 2027; main center closes July 2027 with targeted reopenings May–December 2028; Ice Arena to remain open and Parks offices will temporarily relocate to the Government Center.

The full story

Staff described a phased construction approach intended to keep parts of the facility open as long as possible while major renovations proceed. Key milestones provided to the Working Group included the September 2026 closure of Grove Cove Aquatic Center for construction, a March 2027 scheduled closure of the Gymnasium and Teen Center, and a July 2027 closure of the Main Community Center (including Maple Maze, Senior Center and meeting and rental spaces).