Applicant says two recharge basins and underground storage will reduce runoff; neighbors remain skeptical

Oct 29, 2026

Applicant engineer testified the site will include two sand‑bottom recharge areas and underground storage, and argued the design reduces peak runoff; residents said the area floods frequently and pressed for robust documentation and perpetual maintenance funding (O&M manual estimated at ~$21,000/year).

The full story

Engineer Sharif Ali told the board the stormwater approach includes shallow sand‑bottom recharge areas and underground piping to reduce peak discharge from the site, and that because most of the lot is previously developed the project qualifies as a minor stormwater development under current state rules.