Committee approves multiple water and sewer capital projects, PFAS testing transfer

Oct 30, 2026

The committee approved contracts for a Ward Water Treatment Plant tank recoating ($181,907), East Side Wastewater clarifier installation ($240,000), Upper Boulding sanitary sewer rehab ($2,207,480.43) and CHA inspection and pre‑resurfacing camera/cleaning task orders; staff also transferred $200,000 from PFAS settlement funds for lab testing and program planning.

The full story

Water Resources Director Allison Craft presented and the committee approved a suite of capital actions covering water storage, wastewater clarifier installation, sewer rehabilitation and related engineering inspection services.