Public Works outlines proportionality, says developer’s off-site share is about one-third under current model
Oct 28, 2026
Oct 28, 2026
Public Works told the commission the developer would pay roughly 33% of needed off-site improvements on Hilliard under current AM-peak trip modeling (88 existing vs. 29 new trips); staff urged a 12-month negotiation with ODOT to settle access and final proportionality.
The full story
Public Works staff explained to the Klamath County Planning Commission that off-site transportation improvements associated with Hill Haven Estates will be split by proportionality — the developer pays the share of improvements equal to their contribution to new traffic. Staff said the current traffic-impact study counts 88 existing AM-peak trips and 29 projected new AM-peak trips from the north phase.